View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7526
Project Title: Exterior Led Lighting (HCC)
Agency: HCC
Division: HCC
Department: NDOC
Project Manager: CAD
Description: Humboldt Conservation Camp Pole Lighting
Location: Winnemucca
DI_Location_2: 0
Project Description: This request is for the installation of light poles including fixtures, controls, trenching, conduit, wiring and connections to existing utilities.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Poles with Lighting (18 ea @ $7,000/ea) 126,000
2 Wall Mounted Fixtures (13 ea @ $1,500/ea) 19,500
3 Conduit, Conductors, Trenching & Repairs (3,200 lf @ $50/lf) 160,000
4 Lighting Controls 10,000
5
6
7
8
9
10
11
12
13
14
15
16
Total 315,500