View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7523
Project Title: Heat Pump and Piping Replacement (Desert Research Institute)
Agency: DRI
Division: DRI
Department: NSHE
Project Manager: BBM
Description: This project will replace the heat pumps and associated piping at the Desert Research Institute in Las Vegas.
Location: Las Vegas
DI_Location_2: 0
Project Description: This project will replace the existing heat pumps and the heat pump piping loop within the building and at the central plant at the Desert Research Institute Southern Nevada Science Center.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Piping Replacement (Central Plant & Building) 300,000
2 Piping Insulation 6,500
3 Water Source Heat Pump (5 ton) (2 ea @ $14,000/ea) 28,000
4 Water Source Heat Pump (4 ton) (2 ea @ $13,000/ea) 26,000
5 Water Source Heat Pump (3 ton) (10 ea @ $12,000/ea) 120,000
6 Water Source Heat Pump (2.5 ton) (7 ea @ $11,000/ea) 77,000
7 Water Source Heat Pump (2 ton) (16 ea @ $10,000/ea) 160,000
8 Water Source Heat Pump (1.5 ton) (6 ea @ $9,000/ea) 54,000
9 Water Source Heat Pump (1 ton) (3 ea @ $8,000/ea) 24,000
10 Piping Modifications & Accessories 240,000
11 Ductwork Modifications 50,000
12 Electrical Modifications 45,000
13 Demolition/Rigging 30,000
14 Ceiling Grid Removal/Replacement (20,000 sf @ $10/sf) 200,000
15 Temperature Controls 200,000
16 Testing & Balancing/Commissioning/Water Treatment 115,000
Total 1,560,500