Application ID: 7521
Project Title: Direct Digital Control System Upgrade (Nevada Youth Training Center)
Agency: NYTC
Division: CFS
Department: DHHS
Project Manager: TJD
Description: This project will upgrade the direct digital control system that serves the various buildings at the Nevada Youth Training Center.
Location: Elko
DI_Location_2: 0
Project Description: The scope of work for this project includes a complete direct digital control system for the entire NYTC campus. This project includes HVAC control work at the Administration Building, Education Building, five (5) Dormitory Buildings, Frontier/Adventure Dormitory Building, Multipurpose Building, and Gymnasium Building. Additionally, lighting controls will be added and integrated with the direct digital control system for the buildings listed above.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Control Components 30,000
2 Temperature Control System Hardware & Software 250,000
3 Variable Frequency Drives 50,000
4 Programming & Graphics 30,000
5 Testing, Balancing, & Commissioning 20,000
6 Lighting Control Integration with DDC 7,500
7
8
9
10
11
12
13
14
15
16
Total 387,500