SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7520
Project Title: ADA Upgrades Nevada Youth Training Center
Agency: NYTC
Division: CFS
Department: DHHS
Project Manager: MCR
Description: Remodel Administration Building Restrooms, Classroom / Infirmary Restrooms & Industrial / Vocational Restrooms for ADA Compliance
Location: Elko
DI_Location_2: 0
Project Description: This Project will remodel the interior of the Administration, Classroom / Infirmary and Industrial / Vocational buildings and add ADA signage to the Gym restrooms. The work will consist of restrooms, door hardware and signage to comply with the American w

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Administration Restroom Remodel (2 ea @ $10,000/ea) 20,000
2 Infirmary Unisex Client Restroom Remodel 35,000
3 Classroom Restroom Remodel (2 ea @ $30,000/ea) 60,000
4 Industrial/Vocational Unisex Restroom Remodel 18,000
5 Mechanical / Electrical Modifications 5,000
6 Interior ADA Signage (6 ea @ $350/ea) 2,100
7 Door Hardware (6 ea @ $700/ea) 4,200
8 Door Threshold 700
9.
10.
11.
12
13
14
15
16
Total 145,000