View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7518
Project Title: Magnetic Door Lock System (Mountaineer & R&C Buildings)
Agency: NYTC
Division: CFS
Department: DHHS
Project Manager: CAD
Description: This project replaces doors, door locks and door controls in these two buildings.
Location: Elko
DI_Location_2: 0
Project Description: This project will replace the existing doors, door locks and door controls in the Mountaineer and Explorer (R & C) Cottages. This project is the start of a campus wide magnetic door lock upgrade and will also include the installation of a new system in the R&C building. It is expected that this project will be repeated over time for all buildings when requested and approved.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Replace Door Controls with Locks (46 ea @ $4,000/ea) 184,000
2 Architectural Repairs (46 ea @ $450/ea) 20,700
3 Door Replacement (46 ea @ $2,500/ea) 115,000
4 Replace Combiner Boxes (4 ea @ $8,000/ea) 32,000
5 Badging Equipment 20,000
6
7
8
9
10
11
12
13
14
15
16
Total 371,700