View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7513
Project Title: Replace Evaporative Coolers and Exhaust Fans (Nevada Youth Training Center)
Agency: NYTC
Division: CFS
Department: DHHS
Project Manager: TJD
Description: This project will replace the existing evaporative coolers, exhaust fans, ductwork, air distribution, and controls.
Location: Elko
DI_Location_2: 0
Project Description: The scope of work for this project includes a complete renovation of the evaporative cooling and ventilation exhaust fan systems serving six (6) NYTC Dormitory Buildings. The project includes replacing the existing evaporative coolers, restroom and shower area exhaust fans, domestic water piping, ductwork, air distribution, and related controls.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Equipment & Piping 13,000
2 Evaporative Cooler (9 ea @ $6,000/ea) 54,000
3 Exhaust Fan (Building Relief) (9 ea @ $6,000/ea) 54,000
4 Exhaust Fan (Restroom) (6 ea @ $4,000/ea) 24,000
5 Ductwork & Air Distribution Modifications 16,500
6 Backflow Preventer & Piping (6 ea @ $5,000/ea) 30,000
7 Temperature Control System Modifications 85,000
8 Testing, Balancing, & Commissioning 20,000
9 Crane/Rigging 7,500
10 Electrical Modifications 40,000
11
12
13
14
15
16
Total 344,000