SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7511
Project Title: Upgrade Irrigation System (Nevada Youth Training Center)
Agency: NYTC
Division: CFS
Department: DHHS
Project Manager: BJW
Description: Replace existing irrigation facilities campus wide.
Location: Elko
DI_Location_2: 0
Project Description: The project will design and construct a campus-wide replacement of the irrigation water systems at the Nevada Youth Training Center (NYTC). The sports field irrigation system is in good condition and will not be included with this project. The project scope includes abandonment of the existing irrigation facilities, installation of new irrigation mains, valves, sprinkler heads, and control wiring. If possible, recently upgraded sprinkler heads will be reused.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Irrigation System Replacement (20 acres @ $25,000/acres) 500,000
2 Site Restoration & Reseeding 50,000
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 550,000