View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7510
Project Title: Pavement Maintenance and Repair (Nevada Youth Training Center)
Agency: NYTC
Division: CFS
Department: DHHS
Project Manager: MJM
Description: Crack seal, slurry, repair & re-stripe existing pavements.
Location: Elko
DI_Location_2: 0
Project Description: This project will provide concrete gutter repair, utility vault cover replacement, miscellaneous AC patching, crack sealing, slurry sealing and ADA parking replacement.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Replace & Extend PCC Valley Gutter (300 lf @ $30/lf) 9,000
2 Seal Large Cracks (5,000 lf @ $2/lf) 10,000
3 Seal Small Cracks (12,000 lf @ $1/lf) 12,000
4 Cutting & Patching (3,000 sf @ $5/sf) 15,000
5 Replace Utility Covers & Collars 20,000
6 Replace PCC Curb & Gutter (50 lf @ $20/lf) 1,000
7 Replace ADA Parking (2,000 ea @ $15/ea) 30,000
8 Seal Coat (300,000 ea @ $.25/ea) 75,000
9 Striping 3,000
10
11
12
13
14
15
16
Total 175,000