View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7507
Project Title: Exterior Energy Retrofit 2 Cottages (Nevada Youth Training Center)
Agency: NYTC
Division: CFS
Department: DHHS
Project Manager: RLC
Description: Upgrade windows, doors and exterior walls of the Adventurer and Mountaineer Cottages at the Nevada Youth Training Center in Elko
Location: Elko
DI_Location_2: 0
Project Description: The scope of this project will retrofit the exterior walls, windows and doors of the Adventurer and Mountaineer Cottages for energy conservation purposes. The retrofit will add an exterior insulating finishing system (EIFS) to the un-insulated masonry buildings/walls and will replace un-insulated steel doors & single pane windows with insulated doors and window units.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition/Disposal 13,475
2 Thermal Window Frames (853 sf @ $53/sf) 45,209
3 Insulated Polycarbonate Glazing (853 sf @ $90/sf) 76,770
4 Exterior Steel Doors (9 ea @ $3,500/ea) 31,500
5 Masonry Repair 12,250
6 Patching, Painting & Sealing 4,900
7 Exterior Insulating Finish System (5,600 sf @ $27/sf) 151,200
8.
9.
10
11
12
13
14
15
16
Total 335,304