Application ID: 7498
Project Title: Exterior Site Lighting Upgrade (NYTC)
Agency: NYTC
Division: CFS
Department: DHHS
Project Manager: CAD
Description: Install new exterior lighting at the Nevada Youth Training Center in Elko.
Location: Elko
DI_Location_2: 0
Project Description: This project will overhaul the entire facility's exterior lighting around all walkways by installing new light poles, fixtures, controls, conduit and conductors.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Poles with Lighting (36 ea @ $7,000/ea) 252,000
2 Conduit, Conductors, Trenching & Repairs (4,000 lf @ $50/lf) 200,000
3 Lighting Controls 25,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 477,000