View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7497
Project Title: HVAC Systems Renovation (Washoe County Armory)
Agency: NArmyNG
Division: NArmyNG
Department: Military
Project Manager: TJD
Description: Replace existing rooftop units, make-up air units, ductwork, and controls.
Location: Stead
DI_Location_2: 0
Project Description: The scope of work for this project includes a complete renovation of the existing heating and cooling systems servicing the Washoe County Armory. The project includes replacing the existing make-up air units, rooftop units, heat pumps, ductwork/air distribution, and related controls.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Equipment & Piping 65,000
2 Make-Up Air Units (20,000 cfm total) 125,000
3 Packaged Rooftop Unit (3 tons) (2 ea @ $10,500/ea) 21,000
4 Packaged Rooftop Unit (4 tons) (5 ea @ $13,000/ea) 65,000
5 Packaged Rooftop Unit (5 tons) 15,500
6 Packaged Rooftop Unit (7 tons) 19,500
7 Packaged Rooftop Unit (10 tons) (3 ea @ $26,500/ea) 79,500
8 Unit Heater, High Efficient (11 ea @ $7,500/ea) 82,500
9 Split Heat Pump System (Up to 5 Zones) (2 ea @ $17,500/ea) 35,000
10 Exhaust Fan, Rooftop (8 ea @ $5,500/ea) 44,000
11 Flue & Combustion Air Modifications 30,000
12 Air Distribution & Ductwork Modifications 30,000
13 Temperature Control System Modifications 230,000
14 Testing, Balancing, & Commissioning 45,000
15 Crane/Rigging 15,000
16 Electrical Modifications 75,000
Total 902,000