Application ID: 7483
Project Title: Air Handler Replacement & Control System Upgrade (University of Nevada, Reno)
Agency: UNR
Division: UNR
Department: NSHE
Project Manager: TJD
Description: Replace existing air handlers, ductwork, piping, and controls (Lombardi Recreation, Mack Social Science, & Fleischmann Agriculture)
Location: Reno
DI_Location_2: 0
Project Description: The scope of work for this project includes the replacement of eighteen (18) indoor air handlers serving Fleischmann Agriculture, Mack Social Science, and Lombardi Recreation Center Building at the University of Nevada, Reno. The project includes replacing the existing air handlers, piping, ductwork, and related controls.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Equipment & Piping 12,000
2 Indoor Air Handlers, Lombardi Recreation (200,000 cfm) 1,400,000
3 Indoor Air Handler, Mack Social Science (70,000 cfm) 490,000
4 Indoor Air Handler, Fleischmann Agriculture (60,000 cfm) 420,000
5 Air Distribution & Ductwork Modifications 135,000
6 Hydronic Piping & Accessories 300,000
7 Temperature Control System Modifications 650,000
8 Testing, Balancing, & Commissioning 80,000
9 Crane/Rigging 40,000
10 Electrical Modifications 60,000
11
12
13
14
15
16
Total 3,587,000