View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7481
Project Title: Advance Planning: Regional Medical Facility (Southern Desert Correctional Center)
Agency: NDOC
Division: NDOC
Department: NDOC
Project Manager: JJD
Description: Site adapt the Prison 8 Regional Medical Facility design from the Prison 8 site to a location immediately adjacent to SDCC.
Location: Indian Springs
DI_Location_2: 0
Project Description: The scope of this project will complete the planning through construction documents for the future 64,381 sf Regional Medical Facility (RMF) with support structures as required, to be built adjacent to Southern Desert Correctional Center. The RMF design from Prison 8 will be updated for current code requirements. The other improvements will be designed through construction documents.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Regional Medical Facility (64,381 sf @ $626/sf) 40,302,506
2 Guard House / Tower / Sally Port (1,433 sf @ $843/sf) 1,208,019
3 Mechanical Upgrades 4,500,000
4 Site Work & Security Fencing 9,472,169
5
6
7
8
9
10
11
12
13
14
15
16
Total 55,482,693