View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7480
Project Title: Renovate Classrooms
Agency: UNR
Division: UNR
Department: NSHE
Project Manager: RLC
Description: Renovate classrooms to upgrade technology, furnishings and lighting.
Location: Reno
DI_Location_2: 0
Project Description: This project includes the renovation of approximately 20 classrooms in the Ansari Business Building, William J. Raggio Building, Edmund J. Cain Hall, and Mack Social Science buildings. The renovation measures include replacing worn furniture, whiteboards, window treatments, paint, flooring, and modernizing lighting and ceiling grids. Significant teaching-learning technology upgrades and installations will be made to provide modern projectors, screens, and software.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition (20 ea @ $1,200/ea) 24,000
2 Carpet Tile (12,000 sf @ $6/sf) 72,000
3 Rubber Base (2,000 lf @ $3.5/lf) 7,000
4 Painting (20,000 sf @ $1.6/sf) 32,000
5 Ceilings (12,000 sf @ $3.5/sf) 42,000
6 Lighting (12,000 sf @ $14.5/sf) 174,000
7 Window Covering (20 ea @ $3,200/ea) 64,000
8 White Boards (40 ea @ $800/ea) 32,000
9 Projection Screens (20 sf @ $10,000/sf) 200,000
10 Projector (20 sf @ $2,000/sf) 40,000
11 Electric Power (20 ea @ $2,400/ea) 48,000
12 Monitors (20 ea @ $2,200/ea) 44,000
13
14
15
16
Total 779,000