View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7478
Project Title: Chilled Water Plant Expansion & Site Piping Extension (University of Nevada, Reno)
Agency: UNR
Division: UNR
Department: NSHE
Project Manager: TJD
Description: Expansion of the existing campus chilled water plant and extending chilled water piping to north campus buildings.
Location: Reno
DI_Location_2: 0
Project Description: The scope of work for this project includes the expansion of the campus chilled water plant and extension of chilled water piping. This project will add two (2) modular chiller plants to the central chilled water plant being constructed in the summer of 2016. The addition of this chilled water plant equipment will serve the Edmund J. Cain Hall, Lombardi Recreation, and Lawlor Events Center. Approximately 3,500 feet of chilled water piping will extend to the aforementioned buildings. The piping will be C900 PVC with restrained pipe fittings and direct bury valves.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Removal & Disposal of Existing Equipment 60,000
2 Packaged Chiller Plant (575 tons) (2 ea @ $1,250,000/ea) 2,500,000
3 Site Chilled Water Piping, Valves, & Accessories 860,000
4 Building Chilled Water Piping, Valves, & Accessories 125,000
5 Temperature Control System Modifications 220,000
6 Testing, Balancing, & Commissioning 20,000
7 Crane/Rigging 10,000
8 Electrical Modifications 40,000
9
10
11
12
13
14
15
16
Total 3,835,000