View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7471
Project Title: Replace Kitchen Tile Flooring (Plumb Lane Armory)
Agency: NArmyNG
Division: NArmyNG
Department: Military
Project Manager: RLC
Description: Removal of existing quarry tile flooring and installation of new vinyl flooring.
Location: Reno
DI_Location_2: 0
Project Description: The scope of this project will the remove the kitchen quarry tile flooring and install vinyl flooring.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolish Quarry Tile Flooring (440 sf @ $2.5/sf) 1,100
2 Floor Preparation (440 sf @ $5/sf) 2,200
3 Vinyl Flooring (440 sf @ $18.5/sf) 8,140
4 Coved Base (120 lf @ $10/lf) 1,200
5 Misc Electrical & Plumbing 3,000
6
7
8
9
10
11
12
13
14
15
16
Total 15,640