Application ID: 7465
Project Title: Replace Cell Toilets & Sinks At Housing Units 1-7 (Southern Desert Correctional Center)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: JJD
Description: Replace toilets and sink in cells w/ stainless steel combination fixtures
Location: Indian Springs
DI_Location_2: 0
Project Description: Replace the existing vitreous china toilet/sink combination units in all cells with Stainless Steel combination units. Work includes all fixtures in Housing units 1-7. Unit 8 is already fitted with stainless steel units.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demo Existing Fixtures & Prepare for Unit (784 ea @ $350/ea) 274,400
2 Combination Toilet / Sink Units (784 ea @ $7,000/ea) 5,488,000
3 Water Conservation System (784 ea @ $325/ea) 254,800
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 6,017,200