Application ID: 7463
Project Title: Armory Replacement (Southern Desert Correctional Center)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: JJD
Description: Provide a new Armory
Location: Indian Springs
DI_Location_2: 0
Project Description: The new Armory will consist of a 1,500 sf CMU structure containing an Armory, a Shop Area, a Muster Area for CO / Staff, as well as ADA Compliant Toilets.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Armory Structure (1,500 sf @ $575/sf) 862,500
2 Site - Grading / Pad Preparation 7,500
3 Site - Utilities 48,400
4 Site - Security Fencing (100 lf @ $225/lf) 22,500
5 Fire Sprinkler System (1,500 sf @ $18/sf) 27,000
6 Secure Fencing for Firearms & Ammunition (50 lf @ $300/lf) 15,000
7
8
9
10
11
12
13
14
15
16
Total 982,900