Application ID: 7452
Project Title: Fire Sprinkler and Alarms Installation (SNAMHS)
Agency: SNAMHS
Division: PBH
Department: DHHS
Project Manager: KRS
Description: Building 6 Warehouse fire sprinklers and alarms installation
Location: Las Vegas
DI_Location_2: 0
Project Description: The scope of this project is to install fire sprinklers and fire alarms in SNAMHS Warehouse Building 6.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Fire Alarm Panel 4,500
2 Fire Alarm Installation (5,300 sf @ $3.25/sf) 17,225
3 Fire Sprinkler Underground (100 lf @ $100/lf) 10,000
4 Asphalt Road Cut & Restoration 11,000
5 Fire Riser Installation 9,000
6 Fire Sprinkler Installation (5,300 sf @ $14/sf) 74,200
7
8
9
10
11
12
13
14
15
16
Total 125,925