Application ID: 7449
Project Title: Interior Door Assembly Replacement at Buildings 1 and 2 (S. NV. Mental Health Services)
Agency: SNAMHS
Division: PBH
Department: DHHS
Project Manager: LAR
Description: Removal and replacement of doors and door hardware
Location: Las Vegas
DI_Location_2: 0
Project Description: The scope of this project is to selectively remove and replace existing doors and hardware in Building 1 and 2, provide security hardware in the computer room of Building 1, installation of two door operators in Building 1, provide card key access system for Building 1 and 2, and touch-up paint door frames.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Building 1
2 Selective Custom Wd Drs Replacement (45 ea @ $1,600/ea) 72,000
3 Touch Up Paint 5,550
4 Hardware (45 ea @ $1,000/ea) 45,000
5 Power Door Operators (2 ea @ $1,500/ea) 3,000
6 Card Key Access System 12,000
7 Electrical to Card Readers 15,000
8
9 Building 2
10 Selective Door Replacement (15 ea @ $910/ea) 13,650
11 Custom Wood Doors (4 ea @ $1,600/ea) 6,400
12 Touch Up Paint 2,600
13 Hardware (32 ea @ $1,000/ea) 32,000
14 Card Key Access System 8,000
15 Electrical to Card Readers 7,000
16
Total 222,200