View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7442
Project Title: Patient Restroom Renovation at Rawson Neal Hospital
Agency: SNAMHS
Division: PBH
Department: DHHS
Project Manager: LAR
Description: Renovate patient restrooms
Location: Las Vegas
DI_Location_2: 0
Project Description: The scope of the project is to renovate fourteen patient restrooms at Rawson Neal Hospital with anti ligature lighting, stainless steel toilets, stainless steel sinks, selectively replace the ceiling at the showers, replace wood lockers and plumbing shrouds.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Replace Ceramic Toilets with Stainless (56 ea @ $3,000/ea) 168,000
2 Antiligature Light Replacement (115 ea @ $1,100/ea) 126,500
3 Selective Replacement of Ceilings in Showers 43,000
4 Replacement of Plumbing Shrouds (12 ea @ $3,000/ea) 36,000
5 Replacement of Wood Lockers & Bases 52,000
6 Miscellaneous Architectural Repairs 21,000
7 Replace Ceramic Sinks with Stainless (76 ea @ $800/ea) 60,800
8
9
10
11
12
13
14
15
16
Total 507,300