Application ID: 7441
Project Title: HVAC Renovation - Building No. 4 (SNAMHS)
Agency: SNAMHS
Division: PBH
Department: DHHS
Project Manager: BBM
Description: This project will replace the make-up air and other HVAC units for Building 4 at the Southern Nevada Adult Mental Health Services campus.
Location: Las Vegas
DI_Location_2: 0
Project Description: This project will replace the make-up air unit and other HVAC units on Building No. 4 (Kitchen) at the Southern Nevada Adult Mental Health Services campus in Las Vegas.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Make-Up Air Unit (5500 cfm) 33,000
2 HVAC Split System (5-ton) (2 ea @ $14,000/ea) 28,000
3 HVAC Split System (3-ton) 9,000
4 Electrical 5,000
5 Demolition/Rigging 6,000
6 Temperature Controls 3,000
7 Testing & Balancing 3,000
8 Commissioning 1,500
9
10
11
12
13
14
15
16
Total 88,500