Application ID: 7438
Project Title: Interior and Exterior Assembly Replacement at Building 3 (Stein Hospital)
Agency: NNAMHS
Division: PBH
Department: DHHS
Project Manager: LAR
Description: Removal and replacement of doors and hardware
Location: Las Vegas
DI_Location_2: 0
Project Description: The scope of this project is to remove and replace twenty existing doors and hardware in Building 3 and to adjust the access control system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 High Security Int Drs & Hw (10 ea @ $8,612.5/ea) 86,125
2 Selective Patient Rm Dr Replacement (12 ea @ $910/ea) 10,920
3 High Security Ext Drs & Hw (10 ea @ $9,070/ea) 90,700
4 Storefront Associated with Ext Drs (900 sf @ $113/sf) 101,700
5 Miscellaneous Architectural 9,000
6 Re-Wiring of Doors to Existing Control System 60,000
7
8
9
10
11
12
13
14
15
16
Total 358,445