Application ID: 7437
Project Title: Building 3 Perimeter/Exterior Security Upgrades (Stein Hospital)
Agency: SNAMHS
Division: PBH
Department: DHHS
Project Manager: LAR
Description: Increase the height of the perimeter fence, replace gate locks and install window security bars.
Location: Las Vegas
DI_Location_2: 0
Project Description: The scope of the project is to increase the height of the existing security fence in one of the patios, replace gate locks at all exterior patios with institutional grade locks and install security bars at ten windows on the second floor to prevent/deter elopement.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 High Security Steel Fence Extension (480 sf @ $100/sf) 48,000
2 Additional Steel Post & Footings (7 ea @ $6,000/ea) 42,000
3 Modifications to Existing Steel Fence 20,000
4 Institutional Locks & Gate Modifications (8 ea @ $5,000/ea) 40,000
5 Window Security Bars (10 ea @ $3,500/ea) 35,000
6
7
8
9
10
11
12
13
14
15
16
Total 185,000