Application ID: 7434
Project Title: Exterior Lighting System (Lost City Museum)
Agency: LostCity
Division: MusHist
Department: T&CultAffr
Project Manager: CAD
Description: Install new exterior lighting at the Lost City Museum in Overton.
Location: Overton
DI_Location_2: 0
Project Description: Add twenty-two 30 foot LED lighting poles and provide power and controls for them. This will significantly improve the area lighting for this facility.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Poles with Lighting (22 ea @ $7,000/ea) 154,000
2 Conduit, Conductors, Trenching & Repairs (2,000 lf @ $50/lf) 100,000
3 Lighting Controls 10,000
4 Pavement Repair (1,250 sf @ $60/sf) 75,000
5
6
7
8
9
10
11
12
13
14
15
16
Total 339,000