Application ID: 7432
Project Title: Replace Irrigation Main (CYC)
Agency: CYC
Division: CFS
Department: DHHS
Project Manager: BJW
Description: Replace the irrigation main, install irrigation backflow prevention, and replace the irrigation well pump at the Caliente Youth Center.
Location: Caliente
DI_Location_2: 0
Project Description: The project will design and construct replacement of the site irrigation mains, irrigation controller, and irrigation well pump and controls at the Caliente Youth Center (CYC). The project scope involves irrigation lines, controls valves, sod and sidewalk replacement, an irrigation backflow preventer, well pump, well pump controls, irrigation controller, and irrigation wiring.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Install Irrigation Main with Valves (2,500 lf @ $35/lf) 87,500
2 Sod & Sidewalk Surface Restoration 25,000
3 Install Irrigation Backflow Prevention 15,000
4 Install Irrigation Controller & Wiring 20,000
5 Replace Well Pump & Controls 25,000
6
7
8
9
10
11
12
13
14
15
16
Total 172,500