View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7431
Project Title: CYC Exterior Insulation System and Window Replacement
Agency: CYC
Division: CFS
Department: DHHS
Project Manager: LAR
Description: Add exterior insulation system and replace windows to multiple buildings
Location: Caliente
DI_Location_2: 0
Project Description: The scope of this project is to designed and installed exterior insulation system for multiple buildings. The project also includes, the removal and replacement of the existing single pane window system with new dual-pane and safety glazing in multiple buildings in the Caliente Youth Center.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Remove & Relocate Fire Alarm (10,000 ea @ $1/ea) 10,000
2 Remove & Relocate Mechanical Piping 21,000
3 Concrete Curb for Eifs System (2,820 lf @ $22/lf) 62,040
4 Metal Framing (2,820 lf @ $37/lf) 104,340
5 EIFS System at 8 Residential Units (16,848 sf @ $12/sf) 202,176
6 EIFS System at Administration Building (2,106 sf @ $12/sf) 25,272
7 EIFS System at Old School (9,400 sf @ $12/sf) 112,800
8 Remove Existing Windows & Selective Demolition 99,600
9 Stucco & Wall Repair (244 ea @ $500/ea) 122,000
10 Windows to 8 Residential Units (3,430 sf @ $143/sf) 490,490
11 Building D - Double Pane Windows (900 sf @ $91/sf) 81,900
12 Old School - Double Pane Windows (1,515 sf @ $91/sf) 137,865
13 Paint Touch Up 30,000
14
15
16
Total 1,499,483