View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7428
Project Title: Pavement Maintenance (Caliente Youth Center)
Agency: CYC
Division: CFS
Department: DHHS
Project Manager: MJM
Description: Provide preventative maintenance on the existing asphalt, and replace ADA parking.
Location: Caliente
DI_Location_2: 0
Project Description: This project will perform maintenance on the existing asphalt pavement, and reconstruct an area where the accessible parking has fallen into disrepair.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Patching (1,000 sf @ $10/sf) 10,000
2 Construct ADA Parking (1,000 sf @ $15/sf) 15,000
3 Crack Seal (115,000 sf @ $.15/sf) 17,250
4 Type 2 Slurry (115,000 sf @ $.45/sf) 51,750
5 Striping 8,000
6
7
8
9
10
11
12
13
14
15
16
Total 102,000