View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7426
Project Title: HVAC Replacement - Administration Building(Caliente Youth Center)
Agency: CYC
Division: CFS
Department: DHHS
Project Manager: BBM
Description: This project will replace the HVAC system for the administration building at the Caliente Youth Center.
Location: Caliente
DI_Location_2: 0
Project Description: This project will replace the chilled water HVAC system for the administration building at the Caliente Youth Center.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Air Cooled Chiller (15-ton) 58,000
2 Chilled Water Pump (1.5 Hp) 8,000
3 Piping Modifications 30,000
4 Demolition/Rigging 17,000
5 Electrical 15,000
6 Testing & Balancing 5,000
7 Temperature Controls 25,000
8 Water Treatment 5,000
9 Commissioning 10,000
10 Ceiling Grid & Tile (1,000 sf @ $10/sf) 10,000
11
12
13
14
15
16
Total 183,000