SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7410
Project Title: Advance Planning: Drainage Improvements (Stewart Facility)
Agency: B&G
Division: SPWD
Department: Admin
Project Manager: BJW
Description: Design through construction documents to improve campus drainage facilities.
Location: Stewart
DI_Location_2: 0
Project Description: This project will provide design through construction documents to improve drainage throughout the Stewart Facility. Construction is anticipated to include the installation of an underground stormwater system, paving of the parking lot outside Building 84, repaving of Jacobsen, Gibson and Wa Pai Shone Streets, and abandonment of an existing underground stormwater infiltration system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Repave Jacobsen Way (125,000 sf @ $4/sf) 500,000
2 Repave Wa Pai Shone Avenue (36,000 sf @ $4/sf) 144,000
3 Repave Gibson Avenue (55,000 sf @ $4/sf) 220,000
4 Pave Building 84 Parking Lot (23,000 sf @ $4/sf) 92,000
5 Replace Sidewalk & Curb & Gutter (10,000 lf @ $25/lf) 250,000
6 Striping & ADA Signage 25,000
7 Storm Drain Piping (5,000 lf @ $65/lf) 325,000
8 Storm Drain Manholes (15 ea @ $6,000/ea) 90,000
9 Storm Drain Outfall Structure 10,000
10 Roof Drain Connections to Storm Drain (10 ea @ $5,000/ea) 50,000
11 Abandon Infiltration Basin 10,000
12
13
14
15
16
Total 1,716,000