Application ID: 7404
Project Title: Fire Alarm Centralization (Stewart Facility)
Agency: SPWD
Division: SPWD
Department: Admin
Project Manager: CPC
Description: Interconnection of 17 standalone buildings to a centralized fire alarm panel.
Location: 0
DI_Location_2: 0
Project Description: The scope of this project is to design and install a centralized campus wide fire alarm system. This system would connect all occupied buildings using the existing and future fiber optic loop for the facility. The system would report back to a central p

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Installation of The Master Control Fire Alarm Panel 12,000
2 Replace Existing Fire Alarms (17 ea @ $24,000/ea) 408,000
3 Connect to Existing/Future Fiber Optic Loop (17 ea @ $4,000/ea) 68,000
4 Fire Department Front Entrance Annunciator Panel 28,000
5
6
7
8
9
10
11
12
13
14
15
16
Total 516,000