Application ID: 7395
Project Title: Roofing Replacement, Belrose Building
Agency: Admin
Division: Admin
Department: Admin
Project Manager: MHF
Description: This project would provide for a single ply roofing system
Location: Las Vegas
DI_Location_2: 0
Project Description: This project would provide for a single ply roofing system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition (45,000 sf @ $1/sf) 45,000
2 Pvc Membrane (45,000 sf @ $10.5/sf) 472,500
3 Polyisoyanurate Installation (45,000 sf @ $2/sf) 90,000
4 Nailer (3,000 lf @ $3/lf) 9,000
5 Misc Components (45,000 ea @ $1/ea) 45,000
6 Walk Pads (1,000 lf @ $2/lf) 2,000
7
8
9
10
11
12
13
14
15
16
Total 663,500