View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7390
Project Title: Upgrade Heating and Air Conditioning (Marjorie Russell Research Center)
Agency: MusHist
Division: MusHist
Department: T&CultAffr
Project Manager: DBN
Description: Upgrade the existing heating and air conditioning systems at the Marjorie Russell Research Center in Carson City.
Location: Carson City
DI_Location_2: 0
Project Description: This project includes replacement of the existing heating, ventilating, and air conditioning equipment at the Marjorie Russell Clothing and Textile Research Center in Carson City. The affected areas of the building are utilized to store historical clothing and textile collections.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Packaged Rooftop Unit (5 ton) (2 ea @ $12,000/ea) 24,000
2 Packaged Rooftop Unit (3 ton) 8,000
3 Exterior Duct & Curb Modifications 5,000
4 Gas & Condensate Piping Modifications 2,000
5 Electrical Modifications 2,000
6 Programmable Thermostats (3 ea @ $1,000/ea) 3,000
7 Crane/Rigging 2,000
8 Removal & Disposal of Existing Equipment 2,000
9 Testing, Balancing, & Commissioning 3,000
10
11
12
13
14
15
16
Total 51,000