Application ID: 7386
Project Title: Roof Replacement, Building 21
Agency: NNAMHS
Division: PBH
Department: DHHS
Project Manager: AJL
Description: Replace Single-Ply Roof Membrane
Location: Sparks
DI_Location_2: 0
Project Description: This project would provide for a single ply roofing system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Membrane Tear Off & Disposal (9,400 sf @ $1/sf) 9,400
2 Membrane Installation (9,400 sf @ $10.5/sf) 98,700
3 Misc Components (9,400 sf @ $.5/sf) 4,700
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14
15
16
Total 112,800