Application ID: 7384
Project Title: Roofing Replacement, NNAMHS Hospital Building 25
Agency: NNAMHS
Division: PBH
Department: DHHS
Project Manager: AJL
Description: Replace Single-Ply Roof Membrane
Location: Sparks
DI_Location_2: 0
Project Description: The scope of this project is to remove and replace the roofing system on the Hospital Building #25 at NNAMHS. The new roofing will insure a water tight membrane roofing system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Membrane Tear Off & Disposal (32,000 sf @ $1/sf) 32,000
2 Membrane Installation (32,000 sf @ $10.5/sf) 336,000
3 Sealing High Parapet Walls (15,000 sf @ $3.5/sf) 52,500
4 Misc Components (32,000 sf @ $.5/sf) 16,000
5 Densdek (32,000 sf @ $2/sf) 64,000
6.
7.
8.
9.
10.
11.
12.
13.
14
15
16
Total 500,500