Application ID: 7380
Project Title: Consolidated Services Facility (NNAMHS)
Agency: NNAMHS
Division: PBH
Department: DHHS
Project Manager: RMO
Description: 110,000 sf office building and operations facility; Demolish buildings 2A, 10, 14, 15, 20, 21 and 22; Continuation of 07-C30
Location: Sparks
DI_Location_2: 0
Project Description: This project requests funding for the construction of the Consolidated Services Facility for the Northern Nevada Adult Mental Health System (NNAMHS) agency. The Consolidated Facility will consist of two buildings. The first would be the main office building to consolidate the NNAMHS departments, currently located in widely dispersed older buildings. The new facility design would be consistent with current and anticipated future service delivery models for the field of mental health treatment. The second building would accommodate the Operations & Grounds Departments that are being relocated to the perimeter of the campus. This location provides improved future expansion capabilities and a more convenient location for service deliveries. The consolidated buildings combined square footage is approximately 110,000 square feet. The Consolidated Facility would replace older NNAMHS buildings that have outlived their useful life and would be demolished as part of this project. The buildings to be demolished include 2A, 10, 14, 15, 20, 21 and 22.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Building (110,000 sf @ $400/sf) 44,000,000
2 Site Development (14 acres @ $10/sf) 6,098,400
3 Building Demolition (60,000 sf @ $24/sf) 1,440,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 51,538,400