View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7378
Project Title: Renovate Exterior Finishes (TMCC Red Mountain Building)
Agency: TMCC
Division: TMCC
Department: NSHE
Project Manager: RMO
Description: Stucco repair, and window, door, and roof replacement.
Location: Reno
DI_Location_2: 0
Project Description: The scope of this project is to provide funding for the design and repair of the damaged stucco on the Red Mountain Building’s exterior. It would also replace damaged windows with energy efficient windows. Replacement windows will be double-pane, high efficiency type with tempered glazing where required by code. Doors and hardware in storefront glazing would be repaired or replaced as necessary. In addition, the existing failing roof system will be replaced with a new single ply roofing system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Repair Coating on Stucco (30,000 sf @ $14/sf) 420,000
2 Patch & Replace Stucco (30,000 sf @ $35/sf) 1,050,000
3 Replace Roof Coping (400 sf @ $50/sf) 20,000
4 Replace Hollow Metal Windows (1,400 sf @ $110/sf) 154,000
5 Dual Pane Glazing (1,400 sf @ $90/sf) 126,000
6 Sealant 88,500
7 Roof Drainage at Balconies 17,500
8 Roof Repair at Projections/Bump-Outs 42,000
9 Repair or Replace Storefront Doors & Hardware 40,000
10 Single Ply Roof Replacement (28,000 sf @ $15/sf) 420,000
11
12
13
14
15
16
Total 2,378,000