View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7372
Project Title: Central Plant Renovation (NNAMHS Dini-Townsend Psychiatric Hospital)
Agency: NNAMHS
Division: PBH
Department: DHHS
Project Manager: DBN
Description: Replace existing chiller, cooling tower, boilers, pumps, piping, and controls.
Location: Sparks
DI_Location_2: 0
Project Description: The scope of work for this project includes a complete renovation of the existing central plant (all heating and cooling equipment). The project will include replacing the existing chiller, cooling tower, plate heat exchanger, boilers, pumps, piping, and related controls. Additionally, this project will replace the existing domestic hot water tempering station with an electronic tempering station.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition & Disposal of Existing Equipment 20,000
2 Dual Circuit Chiller & Cooling Tower (150 ton) 280,000
3 Chilled Water Pumps, Piping, & Accessories 180,000
4 Plate Heat Exchanger 60,000
5 Chiller Room Code Modifications 15,000
6 Boilers (1200 mbh) (2 ea @ $50,000/ea) 100,000
7 Heating Water Pumps, Piping, & Accessories 110,000
8 Flushing, Cleaning, & Chemical Treatment 10,000
9 Boiler Room Code Modifications 5,000
10 Electrical Modifications 20,000
11 Temperature Control System Modifications 190,000
12 Testing, Balancing, & Commissioning 30,000
13 Domestic Hot Water Tempering Station & Pumps 30,000
14
15
16
Total 1,050,000