View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7371
Project Title: Replace Fire-Smoke Dampers (NNAMHS Dini-Townsend Psychiatric Hospital)
Agency: NNAMHS
Division: PBH
Department: DHHS
Project Manager: DBN
Description: Replace existing fire-smoke dampers and interface with direct digital controls.
Location: Sparks
DI_Location_2: 0
Project Description: The scope of work for this project is to remove and replace all of the existing fire-smoke dampers throughout the building. The new fire-smoke dampers would be equipped with monitoring switches such that the facilities staff would be advised should one of the fire-smoke dampers fail or close for any reason.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Fire-Smoke Dampers & Actuators (71 ea @ $500/ea) 35,500
2 Ductwork Modifications (71 ea @ $500/ea) 35,500
3 Temperature Control System Interface (71 ea @ $500/ea) 35,500
4 Programming & Graphics (71 ea @ $150/ea) 10,650
5
6
7
8
9
10
11
12
13
14
15
16
Total 117,150