View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7367b
Project Title: Replace Outdoor Boilers (NNAMHS Buildings 1, 2, & 5)
Agency: NNAMHS
Division: PBH
Department: DHHS
Project Manager: DBN
Description: Replace existing boilers, pumps, piping, and controls at Buildings 1, 2, & 5 at NNAMHS in Sparks.
Location: Sparks
DI_Location_2: 0
Project Description: The scope of work for this project is to replace the existing outdoor gas-fired boilers that serve NNAMHS Buildings 1, 2, and 5. The scope of work will also include replacing the existing heating water pumps and the associated controls.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Outdoor Boiler (620 mbh avg) (3 ea @ $30,000/ea) 90,000
2 Pump & Piping Modifications 70,000
3 Electrical Modifications 9,000
4 Temperature Control System Modifications 30,000
5 Flushing, Cleaning, & Chemical Treatment 10,000
6 Removal & Disposal of Existing Equipment 6,000
7 Testing, Balancing, & Commissioning 9,000
8
9
10
11
12
13
14
15
16
Total 224,000