View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7367a
Project Title: Replace Split System Heat Pumps (NNAMHS Building 3)
Agency: NNAMHS
Division: PBH
Department: DHHS
Project Manager: DBN
Description: Replace existing split system heat pumps and associated controls serving NNAMHS Building 3 in Sparks.
Location: Sparks
DI_Location_2: 0
Project Description: The scope of work for this project is to replace the existing split system heat pumps and the associated controls that serve the pharmacy and some first floor office areas in NNAMHS Building 3.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Split System Heat Pump (4 ton) 7,000
2 Split System Heat Pump (1.5 ton) (2 ea @ $4,000/ea) 8,000
3 Refrigerant Piping Modifications 7,000
4 Ductwork Modifications 14,000
5 Electrical Modifications 4,000
6 Temperature Control System Modifications 12,000
7 Removal & Disposal of Existing Equipment 4,000
8 Testing, Balancing, & Commissioning 4,000
9
10
11
12
13
14
15
16
Total 60,000