View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7366
Project Title: Demolition Building 4(NNAMHS)
Agency: NNAMHS
Division: PBH
Department: DHHS
Project Manager: KRS
Description: Building 4 Demolition and Limited Site Restoration
Location: Sparks
DI_Location_2: 0
Project Description: The scope of this project is to demolish Building 4 at the NNAMHS Campus, remove and relocate utilities, and limited site restoration.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Utility Abandonment & Relocation (19,325 sf @ $1/sf) 19,325
2 Asbestos Abatement (19,325 sf @ $4/sf) 77,300
3 Crawl Space Asbestos Abatement 28,000
4 Building Demolition (19,325 sf @ $10/sf) 193,250
5 Limited Site Restoration (19,325 sf @ $1.5/sf) 28,988
6
7
8
9
10
11
12
13
14
15
16
Total 346,862