View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7353
Project Title: Rooftop Multi-Zone Unit Replacement (NNAMHS Buildings 2A, 8A, 8B, and 8C)
Agency: NNAMHS
Division: PBH
Department: DHHS
Project Manager: DBN
Description: Replace existing roof-mounted multi-zone heating and air conditioning units at NNAMHS Buildings 2A, 8A, 8B, and 8C.
Location: Sparks
DI_Location_2: 0
Project Description: The scope of work for this project is to replace the existing roof-mounted multi-zone heating and air conditioning units that serve NNAMHS Buildings 2A, 8A, 8B, and 8C.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Multi-Zone Unit (12.5 ton) (4 ea @ $130,000/ea) 520,000
2 Ductwork Modifications (4 ea @ $8,000/ea) 32,000
3 Roofing Modifications (4 ea @ $2,500/ea) 10,000
4 Electrical Modifications (4 ea @ $1,000/ea) 4,000
5 Temperature Controls 60,000
6 Testing, Balancing, & Commissioning 16,000
7 Demolition & Disposal of Existing Equipment 8,000
8 Crane/Rigging 12,000
9
10
11
12
13
14
15
16
Total 662,000