Application ID: 7347
Project Title: Replace Sanitary Sewer Laterals (Northern Nevada Adult Mental Health Services)
Agency: NNAMHS
Division: PBH
Department: DHHS
Project Manager: BJW
Description: Replace the sanitary sewer laterals to Buildings 1, 3, 4, 5, 12, 14, 15, and 17.
Location: Sparks
DI_Location_2: 0
Project Description: This project will design and construct sanitary sewer lateral replacements to Buildings 1, 3, 4, 5, 12, 14, 15, and 17 on the Northern Nevada Adult Mental Health Services (NNAMHS) campus. The project scope includes abandonment of existing sanitary sewer laterals, installation of 6" and 8" sanitary sewer laterals, sanitary sewer manholes, asphalt patching, bypass pumping to facilitate construction, and close circuit (CCTV) inspection of the installed sanitary sewer laterals.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Sanitary Sewer Laterals (1,100 lf @ $130/lf) 143,000
2 Sanitary Sewer Manhole (8 ea @ $6,500/ea) 52,000
3 Pavement Patching (1,100 lf @ $45/lf) 49,500
4 Connect Lateral to Existing (8 ea @ $3,500/ea) 28,000
5 Sewer Bypass Pumping 30,000
6 Camera Pipe Inspections 15,000
7
8
9
10
11
12
13
14
15
16
Total 317,500