Application ID: 7333
Project Title: ADA Upgrades Upgrades to Sierra Regional Center
Agency: SRC
Division: ADSD
Department: DHHS
Project Manager: MCR
Description: Remodel restrooms, door hardware and signage.
Location: Sparks
DI_Location_2: 0
Project Description: This project will remodel buildings 602, 603, 604 for compliance with the Americans with Disabilities Act. Work will include the removal and replacement of door hardware, restroom remodeling, and ADA signage.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Building 602 Remodel One Restroom. 21,240
2 Building 602 Door Hardware (20 ea @ $400/ea) 8,000
3 Building 602 Signage (10 ea @ $350/ea) 3,500
4 Building 603 Remodel One Restroom. 21,240
5 Building 603 Door Hardware (20 ea @ $400/ea) 8,000
6 Building 603 Signage (10 ea @ $350/ea) 3,500
7 Building 604 Remodel Restroom (2 ea @ $21,240/ea) 42,480
8 Building 604 Door Hardware (20 ea @ $400/ea) 8,000
9 Building 604 Signage (10 ea @ $350/ea) 3,500
10.
11.
12
13
14
15
16
Total 119,460