View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7322
Project Title: Boiler Replacement (Ely State Prison)
Agency: ESP
Division: ESP
Department: NDOC
Project Manager: BBM
Description: This project will replace the boilers at the Ely State Prison.
Location: Ely
DI_Location_2: 0
Project Description: This project will replace three hot water boilers in the central plant and two steam boilers in Building No. 10 (Work and Recreation) at the Ely State Prison.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Heating Water Boiler (350 Bhp) (3 ea @ $500,000/ea) 1,500,000
2 Steam Boiler (70 Bhp) 200,000
3 Steam Boiler (40 Bhp) 150,000
4 Circulation Pumps (15 Hp) (3 ea @ $37,500/ea) 112,500
5 Circulation Pumps (5 Hp) (3 ea @ $20,000/ea) 60,000
6 Piping Modifications 400,000
7 Demolition/Rigging 75,000
8 Electrical 40,000
9 Temperature Controls 75,000
10 Water Treatment 12,000
11 Testing & Balancing 20,000
12 Commissioning 20,000
13
14
15
16
Total 2,664,500