View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7320
Project Title: HVAC Replacement - Building 9 (Ely State Prison)
Agency: ESP
Division: ESP
Department: NDOC
Project Manager: BBM
Description: This project will replace the HVAC units for Building 9 (Administration Building) at the Ely State Prison.
Location: Ely
DI_Location_2: 0
Project Description: This project will replace the rooftop air handling units on Building No. 9 (Administration Building) at the Ely State Prison.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Rooftop Air Handling Unit (8,000 cfm) (5 ea @ $90,000/ea) 450,000
2 Ductwork Modifications 75,000
3 Curb adapter (5 ea @ $5,000/ea) 25,000
4 Demolition/Rigging 30,000
5 Electrical 25,000
6 Temperature Controls 60,000
7 Testing & Balancing 25,000
8 Commissioning 20,000
9
10
11
12
13
14
15
16
Total 710,000