View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7313
Project Title: Access and Perimeter Road Upgrades (Northern Nevada Correctional Center)
Agency: NNCC
Division: NNCC
Department: NDOC
Project Manager: MJM
Description: Widen the North perimeter road, and perform pavement maintenance on both the access road and perimeter road.
Location: Carson City
DI_Location_2: 0
Project Description: The scope of this project will entail widening of the North perimeter road to allow for proper ambulance access, as well as, perform needed maintenance on the remainder of the perimeter roads and entry road.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Export, Import & Compact (1,500 cy @ $40/cy) 60,000
2 Grading (40,000 sf @ $.5/sf) 20,000
3 Widen AC Perimeter Road to 24' (40,000 sf @ $5/sf) 200,000
4 Crack Seal (220,000 sf @ $.1/sf) 22,000
5 Microsurfacing (220,000 sf @ $1/sf) 220,000
6
7
8
9
10
11
12
13
14
15
16
Total 522,000