Application ID: 7311
Project Title: HVAC Systems Renovations (Administration, Operations, & Unit 6, Northern Nevada Correctional Center)
Agency: NNCC
Division: NNCC
Department: NDOC
Project Manager: TJD
Description: Replace existing dual-duct terminal units, fan coils, exhaust fans, ductwork, air distribution, ceilings, lighting, and controls.
Location: Carson City
DI_Location_2: 0
Project Description: The scope of work for this project includes the replacement of dual-duct terminal units and a fan coil serving Housing Unit #6 at NNCC and the Administration Building. Additionally, the ductwork throughout the Operations Building will be replaced. The project will include replacing the existing dual-duct terminal units, fan coil unit, piping, ductwork, air distribution, and related controls. Ceilings will need to be removed to access the mechanical equipment and ductwork that will be replaced.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Equipment & Ductwork 50,000
2 Dual Duct Terminal Unit (30 ea @ $1,500/ea) 45,000
3 Fan Coil Unit (300 cfm) 2,500
4 Operations Air Distribution & Ductwork Modifications 90,000
5 Administration Air Distribution & Ductwork Modifications 35,000
6 Housing Unit #6 Air Distribution & Ductwork Modifications 25,000
7 Temperature Control System Modifications 95,000
8 Testing, Balancing, & Commissioning 35,000
9 Electrical Modifications 45,000
10 Ceiling Removal & Replacement (18,000 sf @ $10/sf) 180,000
11 Interior Lighting Replacement (18,000 sf @ $8/sf) 144,000
12
13
14
15
16
Total 746,500