Application ID: 7309
Project Title: Insulate Exterior Walls Units 1 - 5 & 10 (Northern Nevada Correctional Center)
Agency: NNCC
Division: NNCC
Department: NDOC
Project Manager: RLC
Description: Insulate exterior walls on Housing Units 1 - 5 and Housing Unit 10
Location: Carson City
DI_Location_2: 0
Project Description: This project includes the design and insulating of the exterior walls on Housing Units 1 through 5 and 10. The exterior side of Housing Units 1 through 5 will receive an exterior insulating finish system (EIFS), and Housing Unit 10 will be insulated on the interior with metal stud walls, insulation and high impact gypsum board.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Eifs @ Hus 1 - 5 (10,825 sf @ $35/sf) 378,875
2 Wall Insulation @ HU 10 (6,650 sf @ $10/sf) 66,500
3 Painting @ HU 10 (6,650 sf @ $2/sf) 13,300
4 Misc Electrical & Plumbing Adjustments 20,000
5
6
7
8
9
10
11
12
13
14
15
16
Total 478,675